Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Frequent iteration reviews provide early feedback, help validate the product, and reduce costly rework. The PM should explain the value rather than simply requiring attendance. A ❌ — Escalation is unnecessary. B ❌ — Attendance requirements alone don't explain the benefit. C ✅ — Educates the stakeholder on why frequent reviews are valuable. D ❌ — Reducing participation may decrease valuable stakeholder feedback. 👉 Answer: C