Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is C. Why? Since the project manager uses a hybrid approach and the scope has unclear requirements, they should use an adaptive/agile component to progressively clarify the requirements. A ❌ Ignore unclear requirements → creates risk and potential rework. B ❌ Wait until everything is clear → delays progress; hybrid approaches allow progressive elaboration. C ✅ Break down and prioritize requirements → enables iterative delivery, feedback, and refinement as requirements become clearer. D ❌ Escalate and wait for authorization → unnecessary; the PM should manage uncertainty using the appropriate delivery approach.