Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The stakeholder engagement assessment matrix classifies each stakeholder's current and desired engagement level (Unaware, Resistant, Neutral, Supportive, Leading). It visually shows gaps between where stakeholders are now and where they need to be, enabling the project manager to develop targeted strategies to close those gaps.