Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
You do not "guide" resources backwards on stages as suggested in A.
Two members were replaced, so the team needs time to rebuild trust, relationships, and working dynamics. A team-building activity can help the new team integrate and improve performance. A ❌ — The PM should not deliberately send the team backward through stages. B ❌ — HR is not the first solution. C ✅ — Team building helps restore collaboration and performance. D ❌ — Escalation is premature. 👉 Answer: C