A project manager has been selected to deliver one of an organization's key flagship solutions. Critical success factors include agility, market adaptation, and a quick response to market offerings. What is one of the key activities that the project manager should undertake to ensure company success?
Select one answer.
Marked answer: D
Community Discussion
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Chose D1
Correct Answer: D ✅ Because the project needs agility and quick market adaptation, the PM should regularly review the project plans, objectives, and deliverables and use updated information to make informed decisions.