Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Correct Answer: B. Email, call, or meet with each stakeholder separately to obtain their input. The PM needs stakeholder input for requirements, constraints, and assumptions, but some stakeholders cannot attend a common meeting. Instead of waiting, the PM should use individual communication methods to collect their input. A ❌ — Meeting only available stakeholders may miss important information. B ✅ — Flexible communication ensures all stakeholders can provide input. C ❌ — Lack of availability is not something that needs escalation. D ❌ — The project management plan should be developed with appropriate stakeholder input.