Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
why A not C?
Because Junior tasks are already behind the schedule and its not good to wait until the performance is evaluated. Immediate acction is to pair up with seniors
A. Consider organizing paired work sessions for the junior and senior economists