Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Prioritize business value through incremental delivery instead of delaying or disrupting current work.
Why A is Correct: ✅ 1. Delivering Value Incrementally (PMBOK Principle 2: Deliver Value) A Minimum Viable Feature (MVF) allows for early showcasing of business value without delaying the entire functionality. Even though the back end (Company B) takes longer, a front-end prototype or partial functionality can still provide insights and marketing validation.
Option A makes the most sense. Delivering a minimum viable feature in 2 weeks lets the marketing department showcase some business value early on. This approach provides a compromise, giving a sneak peek while buying time for Company B to finish their part without derailing the current workflow.