Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
there was a similar question and the answer was to include the local community as a stakeholder, and in this question it seems the PM didn't do this!
It's already an issue, don't see how checking the stakeholder engagement plan is going to help to solve the issue.
They argue that ... prior consultation was not done by the project team. What should the PM do first? Check the Stakeholder Engagement Plan and understand if that task was planned.