Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
I don't understand why B would be the answer as it is stated that mass production cannot happen until after certification. Assessing and evaluating won't change that fact. You simply cannot start production until after certification. A is best.
B. Assess and evaluate the certification process and understand the best and worst case scenarios
C in my view. As it says must obtain and 6 months is more than 3 months. SO what is left to assess. Should go for option that will get teh cert in required time. Not clear why it is not C.