According to the provided burnup chart: The blue "Scope" line represents the total scope or work items for the sprint. The red "Completed" line shows the work completed each day. There's a noticeable increase in the "Scope" line around Day 3, indicating that more work was added to the sprint after it started. Given this observation, the best answer is: B. The team is accepting too much work in the sprint after it has started.
Product Owner is on the right to ask the team to add any Story User during the Sprint but the team must negotiate with the PO if accept the task or if accept to switch it for another one, so the final reponsible that accept to add Story Users during the Sprint is the team. he team is accepting too much work in the sprint after it has started.
The correct answer is B. The team is accepting too much work in the sprint after it has started.