Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
C. Note the reasons for the disagreement and let the team proceed
C. Note the reasons for the disagreement and let the team proceed
The project lead should respect the agreed-upon decision-making process and allow the team to proceed with their decision. However, it is important for the project lead to document their concerns and reasons for disagreement, in case any issues arise later in the project. This approach maintains the team's autonomy and promotes trust and collaboration within the team while ensuring that the project lead's concerns are documented and can be addressed if needed.