Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Delays flagged in a multi-location project → Key activities scheduled over overseas holiday periods → Update schedule to reflect holidays + redistribute/share workload across offices
Going with a schedule change required CCB approval. how PM is modifying the schedule without getting and approval for this change. C seems better than D
D. Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage