Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
D. The organization has already decided to switch to Agile. The PM needs to help them define clear guidelines, and then reinforce the new model so that becomes a part of the team.
A is better
A. Assess the situation to understand how the organization's culture impacts the decision-making process, and coach the team toward a new model.