Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
A In this scenario, the business analyst is unable to proceed with their work because the marketing consultant, a key resource, is unavailable to provide the necessary input. Since the consultant is not dedicating the required time to the project, the project manager should escalate this issue to the consultant’s functional manager. The functional manager is responsible for allocating the consultant’s time and can help resolve the issue by prioritizing the consultant’s involvement in the project.
A is not correct from the 'mindset' perspective. Correct answer is C.
C is correct