Audit Coming? Read Project Information Before You Respond The first step by the Project Manager is to Review the project information(such as the project charter, agile metrics, product backlog, definition of done, and existing compliance documentation)
The correct answer is: B. Review the project information. Explanation: To prepare for the audit, the project manager should ensure they have a thorough understanding of the project's details, progress, and compliance with corporate policies. Reviewing the project information will allow the project manager to address any questions the auditors might have and demonstrate due diligence in managing the project. C. Ask the development team to provide compliance information: While the development team might be a source of technical details, it is the project manager's responsibility to gather and review relevant project information ahead of the audit.
B is the right answer