Requirement Change Requested ↓ Document Change Request ↓ Perform Impact Analysis ↓ Change Control Board (CCB) Review ↓ Approved? ↙ ↘ Yes No ↓ ↓ Implement Reject
D. Accept only those changes that are approved by the change control board (CCB) prior to being implemented.
D. Accept only those changes that are approved by the change control board (CCB) prior to being implemented