When capacity drops and new requirements emerge in an agile project, the PM should immediately work with the Product Owner to reprioritize the backlog.
A is the right answer as the velocity will decrease due to loss of ressource and product backlog will get bigger as there are new requirements. It can't be D as this is AGILE so the schedule is not detailed.
This approach focuses on collaboration with the product owner to adjust priorities based on the team's reduced capacity and the addition of new requirements.