Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
When the original scope is complete but the client requests additional work at closure, the PM should first secure formal acceptance of the delivered work and then process the new requirement through formal change control. This maintains governance and protects the project.
D. Obtain formal acceptance for the completed work and submit a change request:
D. Obtain formal acceptance for the completed work and submit a change request.