Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The question does not explicitly state that the team member is available/unavailable after relocation. When information is missing, PMI expects you to: Avoid assumptions and Choose the least disruptive action. So, (D) is the best available answer because it directly addresses team dynamics in a geographically dispersed team.
Team member is relocating, not quitting. Hence, D.
"Doesn't the fact that a team member is relocating abroad imply that they intend to leave the project? I am unsure if it is appropriate to ask someone who is planning to leave the company to participate in the project remotely.