Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Answer: → C. Review the communications management plan. If the problem is about information flow → Communications Management Plan.
Already it is the issue of communication, not knowing the level of information of the stakeholders. The CEO, known as a stakeholder, needs to know what level of information they need to know so the answer is C. Review the communication plan
in this scenario start by reviewing the stakeholder engagement plan then instead of sending five reports you can send one executive summary with key information that the CEO wants to know about the project