Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Answer: → C. Add construction productivity to the risk register and develop a mitigation strategy for site execution. → Flow: [Uncertainty Domain > Identify Risks] → [Risk Management > Lessons Learned + Risk Register Update] → [Qualitative Analysis] → [Plan Risk Responses (Mitigation for Productivity)] → [Monitor Risks + Implement during Execution] → Proactive delay prevention.
C is the correct answer. B will be part of the "mitigation strategy" mentioned in C.
Add the potential risk to the risk register and then find ways to mitigate the risk so it doesn't affect the overall site execution