Answer: → B. Ask the team member to submit a formal change request. → Flow: [Integration Management > Perform Integrated Change Control] → [Submit Formal Change Request] → [Impact Analysis (Scope/Quality + Hidden Risks)] → [Change Control Board / Review Meeting] → [Approve → Update Baselines + Implement] → [Control Scope + Control Quality].
B is the answer in the situation. Submitting a formal change request is the best approach
I think it is A. There is a similar question in SH that asked to reject the solution and focus in the plan. It suggest it is gold plating. Also if the change does not affect the cost and schedule, (possibly not the scope) you would not need a change request. Not sure if that makes sense