- A hybrid approach combines elements of both predictive (waterfall) and adaptive (Agile) methodologies. For example, a project might use predictive planning for hardware procurement and regulatory compliance while using Agile sprints for software development. The PMI ECO 2021 emphasizes that project managers should tailor their approach to the project context.