Answer: → A. Work with the organization's legal department to identify local regulations to ensure project compliance. → Flow: [Integration Management > Develop Project Management Plan] → [Stakeholder Management > Plan Stakeholder Engagement] → [Risk Management > Identify Risks (using EEFs: Local Regulations + Legal Expertise)] → [Manage Stakeholder Engagement (Internal then External)] → [Monitor Risks & Compliance] → Proactive regulatory identification to prevent government issues.
un projet doit toujours respecter les normes et procédures dicter par le pays
In this situation, to avoid lapses and miscommunication in respect to the regulations of country and locality where the new brick and mortar stores will be located. The Project manager needs to work proactively with the company's legal team to ensure that all aspects are covered in regards to legal compliance for the project.