- Avoidance eliminates the risk entirely by changing the project plan or scope. By removing the feature that triggers the risk, the project manager has eliminated the risk completely. This is the most definitive response but may involve trade-offs (losing the feature). Avoidance is appropriate for high-impact risks when the trade-off is acceptable.