Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Acceptance means acknowledging the risk without taking proactive action. This can be passive acceptance (simply documenting the risk) or active acceptance (setting aside contingency reserves). For low-probability, low-impact risks, passive acceptance is often the most cost-effective approach since the cost of other responses would exceed the risk's potential impact.