Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Using the PERT formula: tE = (tO + 4tM + tP) / 6 = (4 + 4(7) + 16) / 6 = (4 + 28 + 16) / 6 = 48/6 = 8 days. The PERT formula gives the most weight to the most likely estimate (4x) while accounting for optimistic and pessimistic scenarios, producing a weighted average that is more reliable than a single-point estimate.