Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Total float (total slack) is the amount of time an activity can be delayed without delaying the project end date. Activities on the critical path have zero total float, meaning any delay in these activities will directly delay the project completion date. This is why critical path activities require the closest monitoring.