Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Schedule Variance (SV) = EV - PV = $180,000 - $200,000 = -$20,000. A negative SV indicates the project is behind schedule. The project has earned only $180,000 worth of work against $200,000 that was planned. Note: Cost Variance (CV) = EV - AC = $180,000 - $210,000 = -$30,000 (also over budget).