Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
D. Liaise with the school to include nonworking project hours during school start and finish times
Emergency project → cannot be postponed Near a school → safety and disruption concerns Balance urgency with stakeholder needs through collaboration and accommodation.
D for sure