Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The project manager should first review the contract terms to understand obligations and penalties, then have a constructive discussion with the vendor about the schedule performance. Together, they should develop a corrective action plan with clear expectations and milestones. Contract termination should only be considered after other remedies fail.