Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The "A" in RACI stands for Accountable, meaning the person who is ultimately answerable for the correct and thorough completion of the task. A fundamental rule of the RACI matrix is that there must be exactly one Accountable person per task to avoid confusion about who has final decision-making authority.