Project Management Professional · PMI
Select 2 answers.
This question asks for 2 answers, but our data marks only 1. Compare with the community discussion below for the full answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Why A and B are correct A. Include the requirements in the product backlog Regulatory requirements are non‑negotiable. The product owner must add them to the backlog so they can be: Prioritised Estimated Planned into future iterations This is the correct agile mechanism for handling new mandatory work. B. Ask the security department for details You cannot implement or estimate a regulation without understanding: What the rule requires The impact on the product The urgency and compliance deadlines Gathering details is the essential first step.
Option A : In agile frameworks, the Product Owner owns the product backlog. Any new feedback, changes, or regulatory requirements discovered during an iteration review must be handed to the Product Owner so they can formally document and incorporate them into the product backlog. Option E : In agile, the cross-functional team is responsible for technical analysis and estimation. Before any work can be scheduled or prioritized, the team must analyze the impact (effort, complexity, and architectural fit) of introducing these new regulations to the existing project scope