Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- When a deliverable does not meet requirements, the first step is to analyze the root cause. Understanding WHY the quality issue occurred is essential before determining the appropriate corrective action. Jumping to a change request, accepting poor quality, or blaming the team does not address the underlying problem.