- Rolling wave planning is a progressive elaboration technique where work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level. As the project progresses and more information becomes available, future work packages are decomposed into greater detail. This is useful for projects with significant uncertainty.