Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The 100% rule is the most important guideline for creating a WBS. It states that the WBS must capture 100% of all the work defined in the project scope — no more, no less. Each decomposition level must represent 100% of the work in the parent element above it. This ensures completeness without gold-plating.