PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Earned Value (EV) represents the authorized budget assigned to the work that has actually been completed at a given measurement point. It is the 'value' of work done. Combined with Planned Value (PV) and Actual Cost (AC), EV enables objective schedule and cost performance measurement. Schedule Variance (SV = EV - PV) and Schedule Performance Index (SPI = EV/PV) use EV to assess schedule performance.