PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Schedule compression is the process of shortening the project schedule duration without reducing scope. It is typically needed when the calculated schedule exceeds the contractual or required completion date, when the project has fallen behind schedule and needs recovery, or when business needs demand earlier completion. The two primary techniques are crashing (adding resources at increased cost) and fast-tracking (overlapping activities at increased risk).