PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A milestone is a significant event or point in the project schedule that has zero duration, representing the achievement of a major deliverable, phase completion, or key decision point. Milestones serve as checkpoints for schedule performance measurement, stakeholder communication, and contract compliance. They should be measurable, specific, and unambiguous. A milestone schedule showing only key milestones is useful for executive communication.