PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A risk-adjusted schedule incorporates the results of quantitative schedule risk analysis (typically Monte Carlo simulation) by adding contingency time or buffers to the deterministic schedule. This produces a more realistic schedule that accounts for uncertainty and risk. The amount of contingency is typically set at a specified confidence level (e.g., P80 — 80% probability of achievement). Risk-adjusted schedules provide stakeholders with more honest expectations.