PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Planned Value (PV), formerly called Budgeted Cost of Work Scheduled (BCWS), is the authorized budget assigned to the work that is scheduled to be completed by a specific measurement point. It represents what you planned to accomplish by now in dollar terms. PV is time-phased — it changes over time as the schedule progresses. The total PV at project completion equals the Budget at Completion (BAC).