PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Crashing involves adding resources (overtime, additional crews, premium shipping, etc.) to critical path activities to reduce their duration and compress the project schedule. It always increases cost because more resources are applied to achieve the same scope in less time. Effective crashing targets activities with the best time-cost trade-off ratio: the maximum duration reduction per dollar of additional cost.