PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Schedule risk analysis uses quantitative techniques like Monte Carlo simulation to assess the probability of meeting schedule milestones and completion dates. By assigning probability distributions to activity durations and running thousands of simulations, it produces probabilistic forecasts (e.g., '80% confidence of completing by date X'). This is far more realistic than deterministic single-point estimates and identifies which activities contribute most to schedule risk.