PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Resource optimization involves adjusting the project schedule to better align resource demand with availability. The two primary techniques are resource leveling (resolving over-allocation by delaying activities, which may extend the project duration) and resource smoothing (adjusting activities within their float to reduce resource demand peaks without extending the project). Both are essential for creating realistic, achievable schedules.