PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Both components directly address "risk response effectiveness from past projects": Risk audits — their entire purpose is to evaluate how effective risk responses were. Were the planned responses implemented? Did they work? Were they sufficient? Past project risk audit results stored as OPAs give you exactly this data. Lessons learned — capture what worked and what didn't across all project activities, including risk management. They're the most classic form of OPA from past projects.
Absolutely its C
the right answer is C not A