PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A trigger is an early warning sign, not the risk event itself or unrelated events. Missing an interim milestone is an early indicator that the vendor may have delivery problems, triggering increased monitoring or contingency activation. Actual late delivery is the realized risk, not a trigger. Project completion and contract signing are unrelated to delivery delay indicators.