PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
D is the best option, to response morfe effective you need to determine the root cause
It lis more effective approach to risk management by addressing the fundamental issues that give rise to risks
A is the correct answer. B is wrong as its not workaround. C is wrong as risk owners are identified in Risk identification process and here the process is manage responses. D is also wrong as root cuase is determined while identify risks. So A is best answer.