PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The vendor assumption is high-risk because it involves unproven capability for a specialized requirement. The vendor has no track record with such deliveries, making this assumption uncertain and potentially impactful if incorrect. Standard tools, established procedures, and normal business operations are typically lower-risk assumptions based on organizational norms.