PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- In a typical RBS, Level 0 is the project root, Level 1 contains primary categories (Technical, External, Organizational, Project Management), Level 2 contains subcategories, and Level 3+ gets more specific. Technical Risks is a primary category, so it appears at Level 1. Specific risk events would appear at lower levels or in the risk register.